India’s indigenous fighter aircraft programme is moving towards a major milestone, with Hindustan Aeronautics Limited (HAL) targeting the delivery of the first squadron of Tejas Light Combat Aircraft (LCA) Mk-1A fighters to the Indian Air Force (IAF) by March 31, 2027. The latest development comes as the aircraft manufacturer works to resolve the remaining technical issues that have delayed the induction of the upgraded fighter.
According to a report published by Hindustan Times on November 24, the Indian Air Force has informed HAL that it is prepared to accept a squadron’s worth of Tejas Mk-1A aircraft by the end of March 2027. HAL has reportedly committed to delivering between 16 and 18 aircraft within this timeframe. The commitment follows a high-level review meeting held at Air Headquarters last week, involving senior officials from the IAF and HAL.
The review also highlighted progress in resolving technical problems affecting the aircraft. Officials familiar with the discussions indicated that hardware-related issues, including those associated with weapons trials, have been resolved. However, some software-related matters, particularly those concerning the radar, are in the final stages of resolution. The IAF is expected to accept the aircraft without compromising its operational capability requirements. HAL must also complete the necessary documentation and obtain the required operational clearances before handing over the aircraft.
The latest commitment follows remarks made by Air Chief Marshal Ashutosh Dixit at the ANI National Security Summit 3.0 in New Delhi on November 16. The Air Chief stated that the Tejas Mk-1A would join the Indian Air Force within the current financial year and that the service expected to receive a complete squadron during this period.
The Tejas Mk-1A is an upgraded version of the original Tejas Mk-1, featuring improvements designed to enhance the aircraft’s operational performance. Its capabilities include an Active Electronically Scanned Array (AESA) radar, beyond-visual-range (BVR) missile integration, an advanced electronic warfare suite and air-to-air refuelling capability. These upgrades are intended to improve target detection, situational awareness and combat effectiveness.
The programme has faced significant delays, with the first deliveries originally scheduled to begin in 2024. Delays in the supply of F404-IN20 engines from American manufacturer GE Aerospace, along with challenges involving weapons integration, radar validation and certification, have affected the original delivery schedule.
The Indian government has placed two major orders for the Tejas Mk-1A programme. The first contract, signed in February 2021, covers 83 aircraft, comprising 73 fighter jets and 10 twin-seat trainers. A second contract, signed in September 2025, covers another 97 aircraft, including 68 fighters and 29 twin-seat trainers. Together, the agreements account for 180 aircraft for the Indian Air Force. Under the latest commitment, HAL is targeting the delivery of 16–18 aircraft by March 31, 2027.
The urgency of the programme is highlighted by the IAF’s fighter squadron shortage. According to the November 24 report, the service currently operates approximately 29 fighter squadrons against an authorised strength of 42.5. The induction of additional indigenous fighters is expected to support its long-term modernisation and operational requirements.
Meanwhile, India’s future combat aircraft development programmes are also progressing. Air Chief Marshal Dixit indicated that the more advanced Tejas Mk-2 could roll out in 2027, while work on the Advanced Medium Combat Aircraft (AMCA), India’s planned indigenous stealth fighter, continues.
If HAL meets its latest commitment, March 2027 could mark an important turning point for the Tejas Mk-1A programme. The delivery of the first squadron would represent a significant step towards strengthening India’s domestic aerospace manufacturing capabilities and supporting the Indian Air Force’s efforts to rebuild its combat strength.